annotation-info

Due to inclement weather, our downtown lobby & the Conservation & Environmental Center are closed on Friday, Nov. 8. If you need assistance, please visit My Account or call us at (719) 448-4800.

Resource-Detail-Hero

Central Bluffs Substation

We are modernizing our infrastructure for sustainability, system resiliency and reliability.

A new substation is needed in the central part of Colorado Springs to replace the capacity of three aging substations. 

After three years of extensive evaluation of 11 potential sites for a new central substation, the chosen site is at the northwest corner of Austin Bluffs Parkway and Goldenrod Drive. This site is most operationally and economically compatible with the needs of our community.

The Central Bluffs Substation project increases operational flexibility and allows for future expansions and technologies.

Your feedback is welcome as we plan this important project, please email engage@csu.org.

An aerial view of the substation footprint at Central Bluffs. The picture shows the substation footprint in yellow, and total area in green.Why this site?

The unique operational and space requirements for the new Central Bluffs Substation drastically limited our options within a part of Colorado Springs that is already well established and developed. Four main reasons led to the selected site over other options. 

  • Being adjacent to an existing transmission corridor.
  • Available parcel size for current and future technology.
  • Multiple access points.
  • Several operational benefits that will ease load at our Cottonwood and Rock Island Substations.

Working with landowners and tenants

This site required the acquisition of seven parcels (four commercial, two residential, and one vacant parcel). We are working proactively with property owners and tenants.

A google maps aerial view of a substation, with graphics outlining the area of the substation and it's footprint.

Anticipated timeline:

  • 2019-2022: Site analysis
  • Feb. 2022: Site identified
  • June 2022 – May 2023: Property acquisition
  • July 20, 2022: Informational meeting no. 1
  • Oct. 18, 2022: Informational meeting no. 2
  • Jan. 2024: Design begins
  • Nov. 2024: Related natural gas work complete
  • Dec. 2024: Demolition/construction starts
  • Spring 2025 (date TBD): Other related water, wastewater, electric and fiber work
  • November 2026: Construction complete

Questions & answers

Why is a new substation needed? Can the existing substations be refurbished/expanded?

We currently have three substations serving large parts of central Colorado Springs. Unfortunately, these substations are rapidly aging and were built years ago when our city was much smaller and customer needs were drastically different.

As the area around these older substation sites developed, the existing locations are severely space constrained to build out the upgrades. Of greater concern, the equipment in these aging substations is becoming difficult and unsafe to maintain and cannot be upgraded to meet current and future demand in the allocated space.

This will impact the long-term reliability of electrical service for your area. By combining the three aging substations into one site at a new location, we are implementing an innovative, optimized solution to satisfy urgent needs around safety, reliability and cost.

Sustainable Energy Plan projects

Our vision is coming to life. We’re working on projects across our community that improve the electric grid, reduce emissions, increase clean energy use and provide safe, affordable energy for our community.

Jackson Fuller Energy Storage Thumbnail
Current project

Jackson Fuller Energy Storage

Jackson Fuller energy storage uses large-scale lithium-ion batteries to store energy. It supports renewable sources like solar and wind by storing excess energy for use when it's needed. Jackson Fuller energy storage uses large-scale lithium-ion batteries to store energy. It... Jackson Fuller energy storage uses large-scale lithium-ion batteries to store energy. It supports renewable sources like solar and wind by storing excess energy for use when it's needed.

Learn more Learn more
Kelker Substation 1920px
Current project

Kelker Substation Expansion

The Kelker Substation Expansion Project almost doubles the substation's size to accommodate growing energy demands in southeast Colorado Springs. The Kelker Substation Expansion Project almost doubles the substation's size to... The Kelker Substation Expansion Project almost doubles the substation's size to accommodate growing energy demands in southeast Colorado Springs.

Learn more Learn more
Kelker South Thumb 1920
Current project

Kelker-South Plant Transmission Line

The Kelker-South Plant Transmission line project connects two of our existing substations, improving system reliability and meeting growing demand. The Kelker-South Plant Transmission line project connects two of our existing... The Kelker-South Plant Transmission line project connects two of our existing substations, improving system reliability and meeting growing demand.

Learn more Learn more
Drake Progress August 2024 1920
Current project

Martin Drake Power Plant Demolition

After less than two years of careful mitigation efforts, major demolition efforts of the former Martin Drake Power Plant are complete. After less than two years of careful mitigation efforts, major demolition efforts of the... After less than two years of careful mitigation efforts, major demolition efforts of the former Martin Drake Power Plant are complete.

Learn more Learn more
Pike Solar 1920 px
Completed project

Pike Solar Facility

The Pike Solar Facility is now generating and delivering electricity. The 175-megawatt solar array, located on 1,310 acres, was placed into operation in December 2023. The Pike Solar Facility is now generating and delivering electricity. The 175-megawatt... The Pike Solar Facility is now generating and delivering electricity. The 175-megawatt solar array, located on 1,310 acres, was placed into operation in December 2023.

Learn more Learn more
Briargate Substation 1920 px
Completed project

Briargate Substation and Transmission Line

The Briargate Substation and Transmission Line project added infrastructure to increase transmission capacity and improve grid reliability. The Briargate Substation and Transmission Line project added infrastructure to increase... The Briargate Substation and Transmission Line project added infrastructure to increase transmission capacity and improve grid reliability.

Learn more Learn more
Completed project

Cottonwood-Fuller Transmission Line

The Cottonwood-Fuller transmission line conductors were replaced to increase its capacity and improve system reliability. The Cottonwood-Fuller transmission line conductors were replaced to increase its capacity... The Cottonwood-Fuller transmission line conductors were replaced to increase its capacity and improve system reliability.

Learn more Learn more
Horizon Substation 1920 px
Completed project

Horizon Substation

The Horizon Substation is a new substation that supports transmission reliability, and the growing electrical distribution needs of our community. The Horizon Substation is a new substation that supports transmission reliability, and... The Horizon Substation is a new substation that supports transmission reliability, and the growing electrical distribution needs of our community.

Learn more Learn more
Midway Kelker 1920 px
Current project

Midway-Kelker Transmission Line

The Midway-Kelker project will upgrade the current transmission line to increase our system’s capacity. The Midway-Kelker project will upgrade the current transmission line to increase our... The Midway-Kelker project will upgrade the current transmission line to increase our system’s capacity.

Learn more Learn more
Williams Creek Substation 1920
Completed project

Williams Creek Substation

Williams Creek Substation was upgraded and expanded to interconnect renewable energy generation and to support a reliable, cost-effective energy system. Williams Creek Substation was upgraded and expanded to interconnect renewable energy... Williams Creek Substation was upgraded and expanded to interconnect renewable energy generation and to support a reliable, cost-effective energy system.

Learn more Learn more