Galley Road Water Main Improvement Project

We have started a yearlong project to replace more than 4,400 feet of water main and add new lining to more than a mile of existing water main. This work will result in enhanced water quality and service reliability for the area.

Motorists are encouraged to plan ahead if this is their normal route. Through access will be maintained throughout the project, but our crews will be working in the roadway.

Project schedule

Phase 1: Moffat Circle to Wooten Road | July 2024 - mid September 2024

Phase 2: Wooten Road to Babcock Road | October 2024 - February 2025

Phase 3: Sand Creek to Space Center Drive | February 2025 - March 2025

Phase 4: across Powers Boulevard | March 2025 to August 2025

*This schedule is subject to change due to unforeseen circumstances

Work hours will typically be Monday - Friday 7 a.m. - 5 p.m. Thank you for your understanding and cooperation while we work to improve our water system. If you have any questions regarding the project, please contact us at engage@csu.org or call (719) 668-7765

Current projects

N. Academy Boulevard water valves replacement project

N. Academy Boulevard water valves replacement project

We are working to improve water service on North Academy Boulevard as part of a three-phase project. We are working to improve water service on North Academy Boulevard as part of a three-phase project. We are working to improve water service on North Academy Boulevard as part of a three-phase project.

Read Now Read Now
Electrical Cable Rejuvenation Program

Electrical Cable Rejuvenation Program

By injecting a silicone-like fluid into underground electrical cables, we can help them last for decades longer, improving reliability and saving ... By injecting a silicone-like fluid into underground electrical cables, we can help them last for decades longer, improving reliability and saving ... By injecting a silicone-like fluid into underground electrical cables, we can help them last for decades longer, improving reliability and saving ...

Read Now Read Now
Kelker Substation Expansion Project

Kelker Substation Expansion Project

The Kelker substation expansion project addresses our plan to improve system reliability and expand resources to meet growing energy demands. The Kelker substation expansion project addresses our plan to improve system reliability and expand resources to meet growing energy demands. The Kelker substation expansion project addresses our plan to improve system reliability and expand resources to meet growing energy demands.

Read Now Read Now
Fiber Network

Fiber Network

Colorado Springs will be one of the best-connected cities in the country, enabling the highest-speed internet connectivity for every home and ... Colorado Springs will be one of the best-connected cities in the country, enabling the highest-speed internet connectivity for every home and ... Colorado Springs will be one of the best-connected cities in the country, enabling the highest-speed internet connectivity for every home and ...

Read Now Read Now
Martin Drake Power Plant

Martin Drake Power Plant

The demolition of the Martin Drake Power Plant has a tentative completion date at the end of 2024, barring unexpected delays. The demolition of the Martin Drake Power Plant has a tentative completion date at the end of 2024, barring unexpected delays. The demolition of the Martin Drake Power Plant has a tentative completion date at the end of 2024, barring unexpected delays.

Read Now Read Now
Central Bluffs Substation

Central Bluffs Substation

The Central Bluffs Substation project will modernize our infrastructure for sustainability, system resiliency and reliability. The Central Bluffs Substation project will modernize our infrastructure for sustainability, system resiliency and reliability. The Central Bluffs Substation project will modernize our infrastructure for sustainability, system resiliency and reliability.

Read Now Read Now
Continental Hoosier System Project

Continental Hoosier System Project

The goal of the Continental-Hoosier System Project is to improve the resiliency, redundancy and efficiency of this important part of our water system. The goal of the Continental-Hoosier System Project is to improve the resiliency, redundancy and efficiency of this important part of our water system. The goal of the Continental-Hoosier System Project is to improve the resiliency, redundancy and efficiency of this important part of our water system.

Read Now Read Now
Smart meters

Smart meters

Upgraded meters allow two-way communication between your home or business and our systems. Upgraded meters allow two-way communication between your home or business and our systems. Upgraded meters allow two-way communication between your home or business and our systems.

Read Now Read Now
Monument Creek stabilization project

Monument Creek stabilization project

Our work to stabilize a section of Monument Creek is complete! Critical wastewater infrastructure that lies beneath the creek bed is now protected. Our work to stabilize a section of Monument Creek is complete! Critical wastewater infrastructure that lies beneath the creek bed is now protected. Our work to stabilize a section of Monument Creek is complete! Critical wastewater infrastructure that lies beneath the creek bed is now protected.

Read Now Read Now
Northern Monument Creek Interceptor Project

Northern Monument Creek Interceptor Project

The proposed Northern Monument Creek Interceptor would save money, improve reliability, plan for growth and ensure compliance with regulations. The proposed Northern Monument Creek Interceptor would save money, improve reliability, plan for growth and ensure compliance with regulations. The proposed Northern Monument Creek Interceptor would save money, improve reliability, plan for growth and ensure compliance with regulations.

Read Now Read Now
South Catamount Dam Rehabilitation Project

South Catamount Dam Rehabilitation Project

We are completing necessary maintenance and improvements to South Catamount Reservoir, preserving and extending the life of the dam for decades to ... We are completing necessary maintenance and improvements to South Catamount Reservoir, preserving and extending the life of the dam for decades to ... We are completing necessary maintenance and improvements to South Catamount Reservoir, preserving and extending the life of the dam for decades to ...

Read Now Read Now
Jackson Fuller Energy Storage Project

Jackson Fuller Energy Storage Project

The Jackson Fuller energy storage project helps us store excess energy for use during periods of low generation or high demand. The Jackson Fuller energy storage project helps us store excess energy for use during periods of low generation or high demand. The Jackson Fuller energy storage project helps us store excess energy for use during periods of low generation or high demand.

Read Now Read Now
Williams Creek Substation

Williams Creek Substation

The Williams Creek substation was expanded to accommodate the new Pike Solar Array and interconnect to the transmission line from the Nixon Power ... The Williams Creek substation was expanded to accommodate the new Pike Solar Array and interconnect to the transmission line from the Nixon Power ... The Williams Creek substation was expanded to accommodate the new Pike Solar Array and interconnect to the transmission line from the Nixon Power ...

Read Now Read Now
Midway-Kelker Transmission Line Project

Midway-Kelker Transmission Line Project

The Midway-Kelker transmission line project supports the Sustainable Energy Plan (SEP) goal to provide safe and reliable energy systems. The Midway-Kelker transmission line project supports the Sustainable Energy Plan (SEP) goal to provide safe and reliable energy systems. The Midway-Kelker transmission line project supports the Sustainable Energy Plan (SEP) goal to provide safe and reliable energy systems.

Read Now Read Now
Kelker-South Plant Transmission Line Project

Kelker-South Plant Transmission Line Project

The Kelker to South Plant transmission line improves system reliability and meets growing electrical demand at a reasonable cost. The Kelker to South Plant transmission line improves system reliability and meets growing electrical demand at a reasonable cost. The Kelker to South Plant transmission line improves system reliability and meets growing electrical demand at a reasonable cost.

Read Now Read Now
Horizon Substation project

Horizon Substation project

The Horizon Substation will help improve system reliability by expanding our resources to meet the growing energy needs. The Horizon Substation will help improve system reliability by expanding our resources to meet the growing energy needs. The Horizon Substation will help improve system reliability by expanding our resources to meet the growing energy needs.

Read Now Read Now
Flying Horse Substation project

Flying Horse Substation project

The Flying Horse Substation facilitates our transition toward the use of more sustainable energy resources. The Flying Horse Substation facilitates our transition toward the use of more sustainable energy resources. The Flying Horse Substation facilitates our transition toward the use of more sustainable energy resources.

Read Now Read Now
Cottonwood-Fuller transmission line project

Cottonwood-Fuller transmission line project

We replaced the conductor (wire) with a better conductor to increase energy flow between Cottonwood and Fuller Substations. We replaced the conductor (wire) with a better conductor to increase energy flow between Cottonwood and Fuller Substations. We replaced the conductor (wire) with a better conductor to increase energy flow between Cottonwood and Fuller Substations.

Read Now Read Now
Briargate Substation & Transmission Line

Briargate Substation & Transmission Line

The Briargate Substation and Transmission Line Project was completed in 2023, and it supports our efforts to deliver reliable energy to our community. The Briargate Substation and Transmission Line Project was completed in 2023, and it supports our efforts to deliver reliable energy to our community. The Briargate Substation and Transmission Line Project was completed in 2023, and it supports our efforts to deliver reliable energy to our community.

Read Now Read Now